If you want to subdivide a larger Subcatchment in SWMM 5 and get around the same peak flow then a good suggestion would be to make sure that (Figure 1):

 

1.   The sum of the new areas equals the original Subcatchment Area and

2.   The sum of the total Width values equals the original Subcatchment Width on the one Subcatchment

3.   The infiltration, percent imperviousness, roughness and depression storage should be the same. 

 

Figure 1.  Subdividing a Subcatchment

via Blogger http://www.swmm5.net/2013/08/how-to-subdivide-subcatchments-in-swmm-5.html

about author

Storm/Sewer Modeler with a 45 yr association with EPASWMM. Now at Autodesk supporting InfoWorks ICM_SWMM Founder http://robertdickinson.org, Chair/TAC at http://CIMM.ORG

robert.dickinson@gmail.com

Storm/Sewer Modeler with a 45 yr association with EPASWMM. Now at Autodesk supporting InfoWorks ICM_SWMM

Leave a Reply

Translate »

Discover more from ICM SWMM & ICM InfoWorks, SWMM5

Subscribe now to keep reading and get access to the full archive.

Continue reading