Simulating a Blocked Pipe in SWMM 5 and InfoSWMM


Note:  For example, you can use the Simulation Elapsed time as the Premise and a complete closure of the orifice as the action to simulate a blockage in a portion of the network.  A circular orifice can be used to simulate a circular pipe and of course a rectangular orifice can simulate a rectangular pipe.

via Blogger http://www.swmm5.net/2013/07/simulating-blocked-pipe-in-swmm-5-and.html